  1. A 'T-beam slab' is cast and cured. The shuttering has to be removed. The right sequence for removal of shuttering is
    1. Base of beam → Sides of beam → Base of slab → Vertical support Wider beam
    2. Base of slab → Sides of beam → Base of beam → Venical support under beam
    3. Base of slab → Sides of beam → Vertical support under beam → Base of beam
    4. Base of beam → Base of slab → Sides of beam → Vertical support under beam
Correct Option: D

In the example of a T-Beam slab which is cast and cured and the shuttering has to be removed, the right sequence for the job is:
base of slab → sides of beam → Base of Beams → vertical support under beam
This is because the Faces of walls, beams and column sides should be removed first as they bear no load.