  1. Following figure shows network for a particular project consisting of four activities.

    Normal duration and crash time for each activity are given below.

    The minimum time required for completion of project is
    1. 9 days
    2. 13 days
    3. 14 days
    4. 19 days
Correct Option: A

Solve, its easy