Direction: A construction project has the following data:

  1. The critical activities of the project are
    1. P, Q. R, V
    2. P, R, S, U
    3. P, Q, T, V
    4. P, S, U, V
Correct Option: C

(P, Q, T, V) & (P, R, V) are critical paths.