  1. For an activity, ‘optimistic time duration’ is 4 days, ‘pessimistic time duration’ is 11 days and ‘mostlikely time duration’ is 8 days. The PERT value of time duration is______ days (up to one decimal place).
    1. 7.8 to 7.9
    2. 8.8 to 7.9
    3. 7.7 to 8.9
    4. 8.5 to 9.0
Correct Option: A

7.8 to 7.9
PERT value of time duration/Expected time (te)

=
(t0 + 4tm + t0)
6

Where, to = Optimistic time, tm = Most likely time, tp = Pessimistic time.
Thus, (te) =
(t0 + 4tm + t0)
6

=
{(4 + (4 × 8) + 11}
= 7.83 days.
6