-
For an activity, ‘optimistic time duration’ is 4 days, ‘pessimistic time duration’ is 11 days and ‘mostlikely time duration’ is 8 days. The PERT value of time duration is______ days (up to one decimal place).
-
- 7.8 to 7.9
- 8.8 to 7.9
- 7.7 to 8.9
- 8.5 to 9.0
Correct Option: A
7.8 to 7.9
PERT value of time duration/Expected time (te)
= | ||
6 |
Where, to = Optimistic time, tm = Most likely time, tp = Pessimistic time.
Thus, (te) = | ||
6 |
= | = 7.83 days. | |
6 |