  1. The optimistic time, the pessimistic time and the most likely time of a job are 6, 13 and 8 days respectively. The variance for this job is ________
    1. 1.145 to 5.56
    2. 4.25 to 1.52
    3. 2.45 to 3.54
    4. 1.34 to 1.37
Correct Option: D

(1.34 to 1.37)

=
(Optimistic + 4 × Most likely + Pessimistic)
6

The variance is given by :
V =
(Pessimistic - Optimistic)
²
6

=
(13 - 6)
² = 1.36
6