Home » Architecture and Planning Miscellaneous » Architecture and Planning Miscellaneous-topic » Question

Architecture and Planning Miscellaneous-topic

Architecture and Planning Miscellaneous

  1. In which of the following models does the private partner own the revenue as well as the risk associated with the project for a limited period of time?
    1. Build, Own, Operate (BOO)
    2. Build, Own, Operate, Transfer (BOOT)
    3. Design, Build, Finance, Operate (DBFO)
    4. Design, Bid, Build (DBB)
Correct Option: B

Build-Own-Operate-Transfer (BOOT) arrangement involves the transfer of responsibility for constructing, financing and operating a single facility to a private sector partner for a fixed period of time. At the end of that period, the responsibility reverts to the public party.