The optimistic, most-likely and pessimistic time for developing a new product are 12 months, 15 months and 17 months, respectively. Calculate the expected time in months.
-
- 12.00 to 14.00
- 14.00 to 15.00
- 14.14
- 15.64
Correct Option: B
Expected Time (te) = | ||
6 |
where, to = Optimistic time, tm = Most likely time, tp = Pessimistic time.
Thus , (te) = | = | = 14.84 months | ||
6 | 6 |