  1. Two concrete mixers of capacity 200 liters each are used in a construction site to produce 20 cubic meter of concrete. Ingredient charging, mixing and discharge times are 3 minutes, 7 minutes and 1 minute respectively. Assuming a time loss of 5 minutes per hour of operation, the total time in hours for the mixers to produce the required amount of concrete will be ___________
    1. 10
    2. 15
    3. 25
    4. 47
Correct Option: A

Capacity of the concrete mixers = 2 × 200 liters

= 2 ×
200
m3 = 0.4 m3
1000

According to question, time taken to produce 0.4 m3 of concrete = 3 + 7 + 1 = 11 mins
Time taken to produce 20 m3 of concrete =
20
× 11 mins = 550 mins
0.4

As tune loss of 5 min is in 1 hour
For 550 mins, =
550
× 5 min = 50 mins
55

Total time required = 550 + 50 = 600 mins = 10 hours.