  1. In a construction project schedule, A is the first activity. Activities B & C follow A. Activity D follows B & C. Activity E follows C. Activity F follows D & E.

    The critical time to complete the project will be
    1. 14 days
    2. 16 days
    3. 17 days
    4. 20 days
Correct Option: C


The critical path is A-B-D-F. And critical time to complete project is 17 days.