In a construction project schedule, A is the first activity. Activities B & C follow A. Activity D follows B & C. Activity E follows C. Activity F follows D & E.
The critical time to complete the project will be
-
- 14 days
- 16 days
- 17 days
- 20 days
Correct Option: C
The critical path is A-B-D-F. And critical time to complete project is 17 days.