  1. A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last ?
    1. 10 days
    2. 20 days
    3. 15 days
    4. 6 days
Correct Option: A

A’s 1 day’s work =
1
20

A’s 4 days’ work =
4
=
1
205

Remaining work = 1 -
1
=
4
55

This part is completed by A and B together.
Now, (A + B)’s 1 day’s work
=
1
+
1
2012

=
3 + 5
=
8
=
2
606015

Now,
2
work is done by (A + B) in 1 day.
15

4
work is done in
5

=
15
×
4
= 6 days
25

Hence, the work lasted for 4 + 6 = 10 days.