  1. If 4 men or 6 women can do a piece of work in 12 days working 7 hours a day; how many days will it take to complete a work twice as large with 10 men and 3 women working together 8 hours a day?
    1. 6 days
    2. 7 days
    3. 8 days
    4. 10 days
Correct Option: B

Using Rule 1,
4 men ≡ 6 women

1 men ≡
6
=
3
woman
42

= women 10 men + 3 women
= 10 ×
3
+ 3 = 18 woman
2

M1D1T1
=
M2D2T2
W1W2

6 × 12 × 7
=
8 × D2 × 8
1W2

⇒ D2 =
6 × 12 × 7 × 2
= 7 days
18 × 8