  1. A, B and C completed a work costing ₹ 1,800. A worked for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much amount will be received by A?
    1. ₹ 800
    2. ₹ 600
    3. ₹ 900
    4. ₹ 750
Correct Option: B

Using Rule 25,
Ratio of wages of A, B and C respectively
= 5 × 6 : 6 × 4 : 4 × 9
= 30 : 24 : 36 = 5 : 4 : 6
∴ Amount received by A

=
5
× 1800
5 + 4 + 6

=
5
× 1800 = ₹ 600