  1. 15 men take 20 days to complete a job working 8 hours a day. The number of hours a day should 20 men take to complete the job in 12 days
    1. 5 hours
    2. 10 hours
    3. 15 hours
    4. 18 hours
Correct Option: B

We can easily to solve this question with the help of given formula ,
M1 D1 T1 = M2 D2 T2
⇒ 15 × 20 × 8 = 20 × 12 × T2

⇒ T2 =
15 × 20 × 8
= 10 hours