  1. A and B can do a piece of work in 18 days, B and C in 24 days, A and C in 36 days. In what time can they do it all working together ?
    1. 12 days
    2. 13 days
    3. 16 days
    4. 26 days
Correct Option: C

(A + B)'s 1 day's work = 1/18
(B + C)'s 1 day's work = 1/24
(A + C)'s 1 day's work = 1/36
Adding 2 (A + B + C)'s 1 day's work = (1/18 + 1/24 + 1/36) = 1/8
∴ (A + B + C)'s day's work = 1/16
Hence, all working together can finish it in 16 days.